Red Line Summer Construction
Ongoing
Thru Sept 6th, shuttle buses replace trains between North Bethesda and Friendship Heights due to summer construction. As a result, Grosvenor, Medical Center, and Bethesda stations are closed. Express shuttle bus service is available between North Bethesda and Friendship Heights.
Aug 10, 2026, 9:40am – Sep 7, 2026, 3:00am
View alert detailsConstruction Impacts
Effective: Mar. 30, 2026 - Sep. 21, 2026
Beginning March 30, 2026, construction will begin on the north side of the Grosvenor–Strathmore Station platform to replace the existing platform edge as part of ongoing customer‑focused improvements ahead of the Summer 2026 Red Line Major Construction shutdown.
Updated: Apr. 11, 2026 2:44 PM
View detailsConstruction Impacts
Effective: Jul. 28, 2025 - Jun. 28, 2027
Metro is building a new mezzanine at the south end of Bethesda Station to connect Metro Rail to the future Purple Line Bethesda Station. The mezzanine will not be accessible until the Purple Line opens in 2027.
Updated: Apr. 7, 2026 1:45 PM
View detailsTemporary Detour
Effective: Apr. 13, 2023 - Dec. 31, 2026
MDOT MTA Purple Line construction crews began work on the new mezzanine that will connect the future Purple Line Station to Metro, MARC, and the Paul S. Sarbanes Transit Center.
Updated: Apr. 7, 2026 1:39 PM
View detailsConstruction Impacts
Effective: Aug. 4, 2025 - Jan. 1, 2028
Learn about the construction impacts due to the Grosvenor-Strathmore Joint Development project.
Updated: Jul. 14, 2026 1:12 PM
View detailsElevator Modernization
Effective: Apr. 21, 2026 - Oct. 15, 2026
Beginning April 21, 2026, Metro will replace the two elevators on the east side of Hungerford Drive (Rt. 355) near the Park Av entrance of the station. During this project, one elevator will be out of service at a time.
Updated: Aug. 5, 2026 11:20 AM
View detailsCanopy and Stairway Project
Effective: Jan. 1, 2023 - Jul. 15, 2027
In January 2023, Metro began a capital project to install a new stairway and canopy at Judiciary Square Station’s north entrance, located at F Street between 4th and 5th Streets NW.
Updated: Aug. 11, 2026 4:50 PM
View detailsCanopy and Stairway Project
Effective: May. 4, 2026 - Dec. 15, 2026
On May 4, 2026, Metro will begin Phase 4 to install the canopy above the station escalators at the Tenleytown – AU East Station Entrance.
Updated: Aug. 11, 2026 5:15 PM
View details