No current alerts for this line

Completed[Jun. 2024 - Aug. 2024]

Scheduled[Jul. 2026 - Sep. 2026]
Effective: Mar. 30, 2026 - Sep. 21, 2026
Grosvenor-Strathmore
Beginning March 30, 2026, construction will begin on the north side of the Grosvenor–Strathmore Station platform to replace the existing platform edge as part of ongoing customer‑focused improvements ahead of the Summer 2026 Red Line Major Construction shutdown.
Updated: Apr. 11, 2026 2:44 PM
View detailsEffective: Sep. 15, 2025 - Jul. 22, 2026
Glenmont
On September 15, 2025, Metro began rehabilitating one of three elevators in the East Parking Garage. One elevator will be out of service at a time, with the remaining two elevators operational.
Updated: May. 12, 2026 7:27 PM
View detailsEffective: Jan. 1, 2023 - Dec. 31, 2026
Judiciary Sq
In January 2023, Metro began a capital project to install a new stairway and canopy at Judiciary Square Station’s north entrance, located at F Street between 4th and 5th Streets NW.
Updated: Apr. 27, 2026 7:11 PM
View detailsEffective: Jul. 28, 2025 - Jun. 28, 2027
Bethesda
Metro is building a new mezzanine at the south end of Bethesda Station to connect Metro Rail to the future Purple Line Bethesda Station. The mezzanine will not be accessible until the Purple Line opens in 2027.
Updated: Apr. 7, 2026 1:45 PM
View detailsEffective: Aug. 4, 2025 - Jan. 1, 2028
Grosvenor-Strathmore
Learn about the construction impacts due to the Grosvenor-Strathmore Joint Development project.
Updated: Apr. 7, 2026 1:55 PM
View detailsEffective: Apr. 13, 2023 - Dec. 31, 2026
Silver Spring
MDOT MTA Purple Line construction crews began work on the new mezzanine that will connect the future Purple Line Station to Metro, MARC, and the Paul S. Sarbanes Transit Center.
Updated: Apr. 7, 2026 1:39 PM
View detailsEffective: Apr. 21, 2026 - Jun. 30, 2026
Rockville
Beginning April 21, 2026, Metro will replace the two elevators on the East side of Hungerford Drive (Rt. 355) near Park Avenue entrance of the station. During this project, one elevator will be out of service at a time.
Updated: Apr. 27, 2026 6:47 PM
View detailsEffective: May. 4, 2026 - Sep. 30, 2026
Tenleytown-AU
On May 4, 2026, Metro will begin Phase 4 to install the canopy above the station escalators at the Tenleytown – AU East Station Entrance.
Updated: Apr. 7, 2026 1:55 PM
View details