New Carrollton South Side Reconfiguration

Advisory Effective: 4/16/18 - 1/31/19

Updated October 1 - Phase 2 construction will be begin on Monday, October 15, 2018

Beginning April 30th, 2018 through Winter 2018, the south side access area of New Carrollton Metrorail Station will undergo a series of re-configurations to improve station access and to build a new connector road.

Initial construction of the station access improvements will have four phases that will impact pedestrian and vehicular access in different ways, including reconfigured intersections, access road and sidewalk closures, and parking space relocations.

Phase 1, April 30 - October 2018

  • Approximately 20 parking spaces will be temporarily closed in Park & Ride Lot 2.
  • The sidewalk next to Bus Bay F will be closed to the public.

New Carrollton reconfiguration phase 1

Phase 2, Late Fall 2018

  • The new exit for Park & Ride Lot 2 will open for use, and the existing exit will close permanently.
  • The current access road off of Garden City Drive will now be a two-way entrance and exit.
  • The crosswalk has been relocated to the south side of the intersection at Garden City Drive and the entrance road.
  • Customers should use the metered Kiss & Ride spaces within the Park & Ride Garage on the first level.

New Carrollton reconfiguration phase 2

For your safety, follow all construction notices and signs

Details of this joint development project are available in the Staff Report: Proposed changes to WMATA facilities at New Carrollton Metrorail Station

This advisory will be updated as additional information becomes available.