SafeTrack Surge #12: Blue Line | Rosslyn to Pentagon


Final Progress Report as of 3/15/17

WORK ZONE:
Rosslyn to Pentagon, Line Segment Shutdown February 11 - February 28

SCOPE OF WORK:
Renewal of rail and track infrastructure on this portion of the Blue Line, including grout pads, fasteners, rail and crossties.

Critical tasks completed during the surge include:

  • Replaced more than 7,800 linear feet of grout pad
  • Replaced more than 5,200 linear feet of rail
  • Replaced more than 5,600 fasteners
  • Replaced almost 700 crossties
  • Welded more than 50 joints
  • Replaced 900 insulators
  • Repaired more than 35 power cables and more than 72 pigtails