Orange Line platform construction update
Published: Tuesday, June 9, 2020
Two weeks into the summer shutdown, construction activity is well underway at Vienna, Dunn Loring, West Falls Church and East Falls Church stations. So far, construction crews have focused on demolition work, including the removal of all tiles from the platforms, mezzanines and pedestrian bridges. They are also preparing for the pouring of new concrete platform edges, including the installation of supportive shoring. Here are some additional highlights from the work that took place at the four Orange Line stations over the past two weeks.
Vienna
Work at the stations includes more than just platform reconstruction. At
Vienna, crews have removed old elevator cladding and started installing a
new grid for ceiling panels in the north pedestrian bridge. They also
finished demolishing windscreen framing bays in the mezzanine to provide
access for the use of a mini-crane needed to lift the heavy granite
platform edges into place. Placing concrete on the platform edges has also
begun.
Vienna – Installing forms along the platform edge (left). View of
construction activity on the platform (right).
Dunn Loring
Crews brought in heavy machinery to demolish the existing platform, including the platform tile and concrete topping slab. With the existing platform edges removed, crews are finishing formwork and rebar for pouring the new concrete edges. They are also removing old light fixtures, installing conduit for new lighting and installing new wiring for an improved fire alarm system.
Dunn Loring – Demolishing the platform topping slab (left). View of the
platform after topping slab demolition (right).
West Falls Church
With all of the old tile removed at West Falls Church station, the team began installing new slip-resistant tiles in the station mezzanine and pedestrian bridge. The installation of the granite platform edge is underway on two sides of the platform, and crews have finished pouring the concrete edges on the other two sides.
West Falls Church – Removing old granite edges from the platform
(left). Installing edge forms in preparation for pouring concrete
(right).
East Falls Church
Crews demolished the asphalt roof and finished hand demolition of the track
edge. They also removed elevator cladding on the platform and demolished
the fire standpipe. New concrete edges have been poured and crews are
prepping to start installing granite edges.
East Falls Church – Protecting the track during saw cutting (left). Saw
cutting concrete and granite edges (right).
To make sure you receive the latest project news and updates on construction progress, follow us on Twitter and Facebook or check back at wmata.com/platformsprogress.