Tuesday, January 26, 2016

12:22 a.m. A Huntington-bound Yellow Line train at L'Enfant Plaza was delayed 17 minutes due to fire department activity.

5:36 a.m. A Huntington-bound Yellow Line train at West Hyattsville was offloaded due to a brake problem. Passengers experienced a 12-minute delay.

7:22 a.m. A Greenbelt-bound Green Line train at Mt. Vernon Square was offloaded due to a track problem. Passengers experienced a 12-minute delay.

7:53 a.m. A Branch Avenue-bound Green Line train at Naylor Road was offloaded due to a track problem. Several trains were single tracked around the incident. Passengers experienced a 12-minute delay.

1:27 p.m. A Largo Town Center-bound Blue Line train at Morgan Boulevard was offloaded due to fire department activity. Blue Line service was suspended between Addison Road and Largo Town Center. Shuttle bus service was provided. Passengers experienced delays up to 30 minutes until approximately 3:15 p.m.

2:11 p.m. A Glenmont-bound Red Line train at Farragut North was offloaded due to a brake problem. Passengers experienced a 5-minute delay.

3:52 p.m. A Branch Avenue-bound Green Line train at L'Enfant Plaza was offloaded due to fire department activity. Passengers experienced a 12-minute delay.

4:41 p.m. A Glenmont-bound Red Line train at Gallery Place was offloaded due to a brake problem. Passengers experienced a 7-minute delay.